Is anyone able to change the requisition accounting information during approvals?  I'd always said no as the req needs to be unreleased but I'm not sure if IPA couldn't do it?

 

Example - user keys in requisition and releases it but the approver wants it to go to a different activity code or use a different GL code.

Scooter
Veteran Member Send Private Message
Posts: 83
Veteran Member
Requisition must be in "unreleased" status to make changes to it.
Kat V
Veteran Member Send Private Message
Posts: 1020
Veteran Member
Yes - but I'm wondering if IPA is sophisticated enough to not close the workunit - unreleased the req, make the approver changes, re-release the req and keep going up the chain?

Don't lose any of the previous approvals but it you are requesting small equipment and it gets to the Admin/CFO level that decide that it's part of an ongoing capital project - right now that unreleased is going all the way back to one and starting over.
David Williams
Veteran Member Send Private Message
Posts: 1127
Veteran Member
I’ve had to something like this and unreleased the requisition within IPA, allowed the Approver to update the distributions and re-released the requisition. I had to add a step at the beginning of the flow to check if an active Workunit already existed for the requisition and if it did, to End the new Workunit.