PO25.6 Line cost changes with add-ins

Sort:
You are not authorized to post a reply.
Author
Messages


Dave Humphrey











Basic Member



Posts: 18




Basic Member



    We have an existing PO25 vendor agreement with many lines on it and we want to change the cost of certain lines/items.  We are trying to use add-ins, but I just can not figure out the correct steps/fields to use to change only certain lines.  Does anyone have instructions?


    Matt_B











    Advanced Member



    Posts: 22




    Advanced Member



      Dave,

      I think what you're missing is the sort option (_f6) and you'll the have to have something like Line number. Here's my simple upload for No-cost items: (This is for Version 10+)

      A - _f2 PVN-Procurement-group
      B- _f8, PVN-Ven-Agrmt-Ref
      C- _f6, Sort-Option
      D- _f14, PT-PVN-ITEM
      E- _f15, PT-PVN-LINE-NBR
      F- _f24, 0:Line-FC1
      G- _f27:0, PVN-Item1
      H- _f28:0, PVN-BASE-COST1
      I- _f32:0, PVN-COST-OPTION1 (this is the no-charge part)



      Kat V











      Veteran Member



      Posts: 1020




      Veteran Member



        To just change the cost, we just map
        _f2 PVN-Procurement-group
        _f8, PVN-Ven-Agrmt-Ref
        _f14, PT-PVN-ITEM OR _f15, PT-PVN-LINE-NBR --- you pick one or the other not both.
        _f24, 0:Line-FC1 C for change
        _f28:0, PVN-BASE-COST1

        upload as change only.


        Dave Humphrey











        Basic Member



        Posts: 18




        Basic Member



          Thanks, we will give it a try and see if we can figure it out.


          Dave Humphrey











          Basic Member



          Posts: 18




          Basic Member



            Thanks, we will give it a try and see if we can figure it out.


            Jeremy











            Veteran Member



            Posts: 129




            Veteran Member



              I'm trying to do something similar. I'm adding lines to my agreement. Then, when I try to use an add-ins upload and FC of "R" for Release Hold on the line, I get a Change Complete, but the line is still on hold.
              Any ideas?
              I have:
              f2, PVN-Procurement-group
              f8, PVN-Ven-Agrmt-Ref
              f15, PT-PVN-LINE-NBR
              f24:0, Line-FC1


              JonA











              Veteran Member



              Posts: 1162




              Veteran Member



                That should work. All I can say is double check your field/column mapping and make sure the agreement is not on hold at the header level.
                Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health