PO25 Review Date

 5 Replies
 0 Subscribed to this topic
 1 Subscribed to this forum
Sort:
Author
Messages
lars
Veteran Member Send Private Message
Posts: 54
Veteran Member

Lawson has a field  in PO25 called  "Review Date". When the vendor agreement is near its expiration date, a notification goes out to the Agreement Administrator.

Has anyone else set this up?

What tool was used? Smart Notification?  Process Flow? Something else?

Can the notification be sent multiple times?

Can more than one email address be used for the notification?

The Lawson IT Group plans to use Smart Notification for this function.

Any information would be helpful.

 

Kat V
Veteran Member Send Private Message
Posts: 1020
Veteran Member
It's intended to be used with the native PO226 report - so a job schedule - not a Smart Note or PF. We haven't used it in years since going to GHX CCX though.
JonA
Veteran Member Send Private Message
Posts: 1163
Veteran Member
I don't know of any notification. Lawson doesn't have a trigger in PF/IPA for this. You could build a report in Crystal that compared Current Date to Review Date and displayed a list of agreements where the review date fell on the the day the report was run.

{POVAGRMTHD.REVIEW_DATE} - CurrentDate = 0

Schedule the report to run daily in LBI. You get mostly blank reports but it would work well on the review days.

Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health
lars
Veteran Member Send Private Message
Posts: 54
Veteran Member
thank you.
lars
Veteran Member Send Private Message
Posts: 54
Veteran Member
Thank you.
lars
Veteran Member Send Private Message
Posts: 54
Veteran Member
Thank you.