Mark
Basic Member Send Private Message
Posts: 17
Basic Member

We've been using Lawson for just over 5 years and our training was abysmal. As we're a small rural hospital we just "make do" with what we know and move on even if it's clearly not the optimal way to do it. I would like to clean up our PO25 files to reflect only items on contract. One of my many issues with this is that Requisition Center templates will not allow an item to be requested (even if on the template) if it's not also on a PO25 so I'm required to have every item on a template also on a PO25, even if it's not on contract! :-( To me this just defies logic and I was wondering if anyone knows how to make this work in Requisition Center without the item being on PO25? Thanks in advance for any suggestions!

Mark
JonA
Veteran Member Send Private Message
Posts: 1163
Veteran Member
That doesn't make sense to me. We have plenty of items on templates that are not tied to a contract. Do you get an error when you try to add a non-contract item to a template?
Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health
JimY
Veteran Member Send Private Message
Posts: 510
Veteran Member
We don't have all of our items on contract either and requesters are able to add them. Is this a set up issue in RQ04?
Mark
Basic Member Send Private Message
Posts: 17
Basic Member
Can someone who has this working send me what they have set up in the RQ04 fields? I'll see if we have something set up wrong.

Thanks!
JonA
Veteran Member Send Private Message
Posts: 1163
Veteran Member

Here are the Main and RQC tabs for a common requester setup.  

Attachments
Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health