Req_number and related PO_number

 1 Replies
 0 Subscribed to this topic
 1 Subscribed to this forum
Sort:
Author
Messages
fategolf
New Member Send Private Message
Posts: 0
New Member
Is there a way to determine the PO_NUMBER that is related to a particular REQ_NUMBER other than using the POLINESRC.SOURCE_DOC_N?
John Henley
Send Private Message
Posts: 3351
That is the correct way (POLINE) to relate Requisitions to Purchase Orders. Keep in mind that it should ideally be done at the line level (REQLINE to POLINE). If you're trying to do this for reporting purposes, make sure you include other key/index fields as well for efficiency purposes.
Thanks for using the LawsonGuru.com forums!
John