Standing inventory issue/order

 9 Replies
 1 Subscribed to this topic
 38 Subscribed to this forum
Sort:
Author
Messages
Sheri
Veteran Member Send Private Message
Posts: 163
Veteran Member

Is there anyway to create a standing inventory issue?

 

We have a department that wants to receive 4 cases of paper every week without having to create a requisition weekly. This paper is a stock item in our warehouse.

 

Kat V
Veteran Member Send Private Message
Posts: 1020
Veteran Member
Not as such - you can make it easier by copying an old req or with quantity filled out on a procurement template. Otherwise you're looking at trying to create some sort of recurring RQ500 with process flow.
Sheri
Veteran Member Send Private Message
Posts: 163
Veteran Member
Thank you for the input, appreciate it.
Mark Silva
Veteran Member Send Private Message
Posts: 1163
Veteran Member
Sheri - Do you have ProcessFlow? I have a simple flow that I think would work for you. It creates a requisition in RQ10 and then releases it. You would have to set up a service and schedule the flow to kick off daily.
Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health
Sheri
Veteran Member Send Private Message
Posts: 163
Veteran Member
Hi Jon, yes we do have process flow, I didn't know that would kick out a req,  I will talk with our programmer on that  Thank you !
Mark Silva
Veteran Member Send Private Message
Posts: 1163
Veteran Member
Let me know if you want me to send you the flow file.
Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health
Sheri
Veteran Member Send Private Message
Posts: 163
Veteran Member

Hi, I was incorrect, we have something 'homemade' that is referred to as "Process flow".  Ours does not have the ability to create the req, only notifies of changes to a field.

 

Thanks Jon,

Sheri

Mark Silva
Veteran Member Send Private Message
Posts: 1163
Veteran Member
You don't have Lawson ProcessFlow Integrator? Or if you already upgraded to Infor 10 it's called Infor Process Automation. Do you have a req approval process?
Jon Athey - Sr. Supply Chain Analyst - Materials Management - MyMichigan Health
Sheri
Veteran Member Send Private Message
Posts: 163
Veteran Member

We do not have Lawson process flow, and are not using a req approval process.

 

 

Sarah
Advanced Member Send Private Message
Posts: 23
Advanced Member
What about setting up a Standard type agreement in PO25.1?