Hi Lawson Team,
I would like to ask if anyone knows how to the system calculates the average leadtime in IC12 if the control code is "R" "need review". I know that if the system control code is "S" "system calculated" it takes the average of previous and last leadtime but for "R", I'm not able to figure out, please help.
In IC226 it says that if the average leadtime is greater than 50% and the item was set for review then it will recalculate and will give a new average cost but not base on the previous and last leadtime.
Regards,
Mike