    Is it possible for the Webrun node to call multiple Post Strings? Specifically, I am trying to load user tasks into PF Admin.  I have the web call established and it works, but it only does one user task at a time, which isn't any real time/effort savings.

    David Williams
    Veteran Member
    Posts: 1127
    Veteran Member
      No, the Lawson web calls will only handle one event at a time. Adding Users and Tasks via WebRuns is much faster than keying them by hand.