I included a word document with screenshots of the issue I'm having.
I have a capital po that is assigned to an activity that is not over budget, based on everything I can see, but it won't let me release the PO because it claims it will PUT me over budget, but it won't.
Please review my attachment. Hopefully that will help explain this. Thank you
You raise an interesting point that we've been struggling with, and possibly I should start another thread about this...
In AC90 we don't feel like we see the full picture. I'm not sure if we have commitments turned on for Reqs, but should we? I did notice that it appears that unreleased PO's don't appear in AC90. We've run into several instances where we think we have money remaining on an activity only to find out a PO was unreleased and we are actually over budget.
Donna - Not trying to dissuade you from tapping into your peers out here on this forum, but I recommend that you open a case with Lawson/Infor (due to the complexity of this particular issue).
I have found Infor support to be pretty good with these types of issues in recent months.